Over $150 Million to Be Invested in Tbilisi International Airport Expansion — What Does the Project Entail?

Over $150 Million to Be Invested in Tbilisi International Airport Expansion — What Does the Project Entail?

An investment project worth more than 150 million US dollars is set to be implemented at Shota Rustaveli Tbilisi International Airport. As part of the expansion, the passenger terminal area will increase by an additional 21 500 square metres, the number of boarding bridges will double from five to ten, and upon project completion, the airport will be able to handle up to 10 million passengers per year.

According to the Ministry of Economy and Sustainable Development of Georgia, expansion works at Tbilisi International Airport are in an active phase and progressing according to schedule. The project is being carried out by airport operator TAV Georgia, whose investment commitments exceed 150 million US dollars.

On November 25, Deputy Minister of Economy and Sustainable Development Tamar Ioseliani reviewed the progress of ongoing works. Information about the project was presented by General Director of United Airports of Georgia Levan Moseshvili and General Manager of TAV Georgia Tea Zakaradze.

Terminal Area to Increase by an Additional 21 500 Square Metres

One of the key components of the project is the expansion of Tbilisi International Airport's passenger terminal. According to information released by the Ministry of Economy on November 25, an additional 21 500 square metres will be added to the total terminal area.

The works encompass the expansion of both arrivals and departures areas, the improvement of passenger service spaces, and the development of new infrastructure.

In addition, the number of passenger boarding bridges providing direct access to aircraft will double — from the current five to ten bridges.

According to initial project details published by TAV Airports in January 2026, the terminal will also include 10 new check-in counters, 24 additional passport control booths, and two new baggage claim carousels. Plans also include upgrading existing zones, developing commercial spaces, and expanding car parking capacity by 500 spaces.

Airfield Infrastructure and New Aircraft Stands

The investment project is not limited to terminal expansion alone. According to the ministry, the works also include modernising airfield infrastructure and constructing new aircraft parking stands.

This component is crucial for boosting the airport's operational capabilities. As passenger traffic grows, the burden on aircraft servicing, parking, ground operations, and all related infrastructure increases accordingly.

TAV Airports' January announcement also highlighted the construction of seven new remote parking stands. The Georgian Ministry of Economy's statement of November 25, 2026 further confirms that airfield infrastructure development is being carried out as part of ongoing works.

Annual Capacity to Increase from 5 to 10 Million Passengers

Following the completion of the project, Tbilisi International Airport's annual passenger capacity will double: it will rise from the current 5 million to 10 million people.

This expansion comes against the backdrop of steady passenger traffic growth in Georgia's aviation market. According to official TAV Airports data, Tbilisi International Airport served over 5.4 million passengers in 2025, demonstrating a 13.7% increase compared to the previous year.

According to the company, 63 airlines operated flights across 71 destinations from Tbilisi in 2025. These figures underscore the scale of the airport's international route network and rising demand.

Furthermore, 2025 was a record-breaking year for Georgia's entire aviation sector. According to the Ministry of Economy, the country's three international airports handled a combined 8.5 million passengers, while the number of completed flights exceeded 37 thousand.

In the event of further passenger traffic growth, expanding existing infrastructure will serve as a vital prerequisite for both attracting new airlines and developing existing routes.

TAV Georgia Management Term Extended Until the End of 2031

The Tbilisi Airport expansion project is being carried out under an agreement signed between the State of Georgia and TAV Georgia in January 2026.

Under the contract, TAV Georgia will continue to operate Tbilisi International Airport until the end of 2031. The previous concession period was scheduled to expire in January 2027.

According to TAV Airports, the volume of investment in airport development will reach approximately 150 million US dollars, with project completion slated for 2028.

According to the Ministry of Economy, the updated agreement also improved financial terms for the state. The annual revenue of United Airports of Georgia from Tbilisi International Airport will triple compared to current levels, and the state will receive an additional 25 million US dollars upfront from the total project amount.

Infrastructure Expansion for Georgia's Aviation Competitiveness

Tbilisi International Airport is a vital link in the country's transport and tourism infrastructure. Expanding its capacity is particularly crucial for developing international air connections, serving tourist flows, and strengthening Georgia's position across the regional aviation landscape.

The project's economic impact goes beyond merely accommodating more passengers. The expanded terminal and upgraded airfield infrastructure are designed to streamline passenger flow management, ease operational constraints during peak hours, and increase the airport's technical capacity to handle more flights and varied aircraft types.

At the same time, infrastructure development alone does not inherently guarantee the arrival of new routes or passenger traffic growth. The ultimate result will depend on commercial airline decisions, the launch of new routes, tourism demand, and the airport's operational efficiency.

As previously noted, the completion of the Tbilisi International Airport expansion project is scheduled for 2028. Its implementation aims to enhance the potential of existing infrastructure and create additional capacity for the continued development of Georgia's aviation sector.