Batumi Artificial Island Project Expands: Footprint to Grow by 25.6 Hectares as Infill Volume Nearly Doubles

Batumi Artificial Island Project Expands: Footprint to Grow by 25.6 Hectares as Infill Volume Nearly Doubles

Ambassador Batumi Island has unveiled an updated master plan for the artificial island and peninsulas, alongside a revised Environmental Impact Assessment report. The changes concern the layout of the reclaimed land, the dimensions and positioning of breakwaters, water circulation across the inner basin, as well as the development of beaches and a yacht marina. The revised schedule extends construction operations until July 2031.


The operational conditions for developing the artificial island in the Black Sea waters off Batumi are changing. Ambassador Batumi Island has submitted an updated Environmental Impact Assessment (EIA) report to the National Environmental Agency, outlining a redesigned layout of the reclaimed territories along with adjusted specifications for protective marine structures, maritime infrastructure, and the construction timeline.

The core concept of the project remains unchanged: two artificial peninsulas, a central artificial island, and three protective breakwaters—western, eastern, and offshore—are still planned. However, the new engineering layout expands the project's overall footprint, alters the relative positioning of structures, and substantially widens the channels connecting the inner basin to the open sea.

The primary engineering goal of these modifications is to improve water circulation and facilitate the unhindered discharge of floodwaters from the Kubastskali River. At the same time, scaling up the project increases the permanently occupied seabed footprint and the total volume of construction materials required.

Spatial Scale of the Project Expands

According to the updated EIA report, the seabed footprint permanently occupied by the development increases from the originally approved 108.19 hectares to 133.79 hectares. This represents an increase of 25.60 hectares, or approximately 23.7%.

The adjustments also encompass the main components of the development:

The largest footprint increase among all components belongs to the offshore protective breakwater: its footprint expands from 4.93 to 19 hectares. According to the EIA report, roughly 55% of the overall spatial expansion is directly attributable to the enlargement of this structure.

It should be emphasized that 133.79 hectares does not refer solely to reclaimed dry land. This metric reflects the entire permanent seabed footprint of the project, combining the artificial land masses with the zones occupied by marine engineering structures.

Offshore Breakwater to Extend by 566 Metres and Shift Deeper into the Sea

One of the project's pivotal modifications involves the engineering design and placement of the coastal defense structures.

Under the initial plan, the offshore breakwater was designed with a length of 630 metres, whereas the updated design extends it to 1,196 metres. In addition, the structure shifts approximately 250 metres further seaward from its original alignment, and its footprint expands from 4.93 to 19 hectares.

The western and eastern breakwaters have also been recalibrated. In the revised design, the western breakwater will reach 1,230 metres and the eastern one 1,280 metres. Compared to the original plans, their lengths increase by 130 and 180 metres, respectively.

The elevation profile of the protective barriers has likewise been revised. In the previous iteration, crest elevations along specific sections of the western and eastern breakwaters ranged between +7.40 and +7.60 metres. In the updated design, the crest height along the main sections is lowered to +4.50 metres, starting at +3.50 metres along the initial shoreline section.

Project engineers explain that the required degree of wave attenuation will be achieved not through structural height, but through a broader cross-sectional profile. As a result, the structures will be lower yet broader and more massive. According to the report, this configuration will deliver efficient wave energy absorption while preserving urban sightlines toward the open sea.

Reclamation Fill Requirements Nearly Double

The enlarged scope of the development requires a substantial surge in the volume of construction materials. The original scheme called for around 3.52 million cubic metres of backfill material to form the reclaimed land and associated marine works. In the updated design, this volume rises to 6.97 million cubic metres.

The EIA report details exact figures: the original requirement was 3,518,488.60 cubic metres, compared with the revised figure of 6,974,800 cubic metres. The difference stands at 3.46 million cubic metres, representing an increase of approximately 98.2%.

At the same time, the armor layer design has been optimized. Instead of the previously planned 20,951 XBloc units, the new approach utilizes a combined system consisting of XBloc+, XBloc, and rock armor. The total quantity of precast concrete armor units has been reduced to 12,068 units, with their total volume decreasing from 74,497 to 68,141 cubic metres.

Consequently, the project calls for an almost twofold increase in rock and soil fill, accompanied by an approximate 8.5% decrease in the total volume of concrete armor units.

Water Circulation: The Driving Factor Behind the Revision

One of the primary catalysts for revising the layout was inadequate water exchange within the inner basin.

The channels separating the central island from the peninsulas were originally designed with a width of approximately 20 metres. However, the revised EIA report reveals that hydrodynamic modeling showed this configuration resulted in sluggish water turnover in certain parts of the inner basin. This created potential risks of stagnant pollutants and sediment buildup discharged by incoming waterways.

In the revised master plan, the water channels are widened to 50–100 metres, with the comparative schedule standardizing the design channel width at 100 metres. This adjustment aims to reinforce hydraulic connectivity between the inner basin and the open sea.

The initial EIA documentation proposed relying on pumping stations and flow accelerators to sustain circulation. The revised approach prioritizes natural hydrodynamic circulation driven by spatial layout: wide channels are engineered to sustain water motion without continuous mechanical pumping.

According to TELEMAC-3D numerical modeling carried out by Yüksel Proje and ARTELIA, the estimated turnover time for 63% of the water volume at monitoring points across the inner basin ranges from 3.6 to 7.5 days, while 95% dispersion of a tracer pollutant across the entire inner basin is reached in 14 days under winter conditions and 15 days in summer.

Nonetheless, these parameters represent numerical modeling outputs rather than absolute guarantees of water quality. The report explicitly highlights that alongside flushing efficiency, the aquatic environment remains significantly affected by organic and microbial loads conveyed by river inflows.

Reconfigured River Discharge Routing

The updated layout also alters the discharge routes of the Bartskhana and Kubastskali rivers, as well as an unnamed ravine channel.

Under the revised scheme, the Bartskhana River will no longer discharge into the inner basin. The Kubastskali River will continue to flow into the eastern section of the inner basin, from where its flow will pass freely into the open sea through the widened channels.

The diversion culvert for the unnamed ravine has been extended from 420 to 482.55 metres. In the new plan, its stream is routed along the shoreline perimeter of the peninsula directly into the open sea, bypassing the inner basin altogether.

Regarding the Kubastskali River, the EIA report also examines the possibility of separately diverting low-flow polluted waters via an intake facility, a pumping station, and a pressurized pipeline. At this stage, this measure remains an exploratory project initiative: detailed engineering has not commenced, and its execution would require separate permitting.

Flood safety assessments were based on the calculated 100-year peak flow for the Kubastskali River—161 cubic metres per second. Hydraulic modeling demonstrated that with 100-metre-wide channels in place, the water level within the inner basin during baseline flood conditions exceeds the peak design sea level by only about one centimetre.

Simultaneously, the study highlights that if channel cross-sections are significantly constricted by siltation or bridge pier placement, localized water level surges could become abrupt. Safe operation of the complex will necessitate ongoing monitoring and periodic maintenance dredging of the waterways.

Two Expansive Beaches and a 108-Berth Marina

Revisions have likewise been introduced to the leisure and maritime infrastructure. The original plan envisaged relatively narrow beach strips approximately 3 metres wide, stretching for 450 and 470 metres. Under the updated concept, these are superseded by two expansive artificial beaches.

The design length of the western beach reaches 830 metres, while the eastern beach extends to 810 metres. In key recreational areas, the beach width will span between 70 and 75 metres.

The marina design has also been upgraded. It is now planned for 108 vessel berths accommodating boats from 20 to 40 metres in length. Berths are divided into four size classes, including 26 dedicated slips for superyachts measuring between 35 and 40 metres.

The marina basin is shielded by offshore breakwaters, with maritime access from the open sea provided through two navigational fairways.

Wave disturbance modeling using the PHAROS suite demonstrated that significant wave heights inside the harbour remain predominantly below 0.40 metres, although specific scenarios at the eastern entrance show values up to 0.41–0.42 metres. The assessment also clarifies that short-period wind waves generated internally within the marina basin were excluded from the model.

Road connectivity to the island will be facilitated by two vehicular bridges, each measuring 90–95 metres in length and 24–27 metres in width. Spanning bridge structures were selected over solid causeways specifically to ensure unobstructed water flow.

Construction Logistics and Environmental Factors

The updated project redesigns site logistics. The worker camp, concrete batching plant, and casting yard for XBloc+ units will be relocated outside the marine construction perimeter to the site of a former oil refinery within the city limits. Finished precast components will be transported to coastal workfronts by road.

Instead of permanent fuel storage tanks within the marine zone, a mobile 15,000-litre refueler will be deployed, while domestic wastewater will be collected in sealed septic tanks and evacuated by licensed waste operators.

From an ecological perspective, the primary negative effect of the enlarged development is the permanent loss of soft-bottom benthic biotopes. In the revised master plan, the permanent seabed footprint reaches 133.79 hectares. Construction operations will temporarily disturb an additional 0.51 hectares of seabed.

EIA specialists conclude that native soft-sediment benthic habitats within the footprint will be virtually entirely eliminated. This impact is classified as localized, permanent, and irreversible. Although the rock and concrete surfaces of marine structures offer hard substrate suitable for colonization by fouling organisms, the report's authors do not consider this an equivalent ecological substitute for the lost seabed. The impact is categorized as moderate and requires compensatory environmental measures.

Special scrutiny was directed toward underwater acoustic impacts on cetaceans. Passive acoustic monitoring conducted in 2025–2026 identified variations in the behavioral patterns of bottlenose dolphins, common dolphins, and harbour porpoises within the construction zone compared to a baseline control site. The researchers emphasize that while the current observation dataset is insufficient to draw long-term population-level conclusions, behavioral sensitivity to construction noise is already evident.

To reduce disturbance, the study recommends halting noisy marine works during nighttime hours (preferably from 20:00), introducing one weekly "quiet day" free from hydrotechnical noise, and expanding the passive acoustic monitoring network from two to four stations.

Construction Scheduled to Run Until July 2031

According to the indicative construction schedule presented in the EIA report, the remaining construction works are programmed between January 2027 and July 2031—spanning a total duration of 55 months.

The longest construction phase will be the offshore breakwater, allotted 36 months from June 2027 to May 2030.

Major marine reclamation activities are scheduled for the favorable weather window between April and October. From November to March, work will continue at lower intensity based on hydrometeorological windows and will be halted during storm warnings.

The document notes that this schedule is indicative: project progress remains subject to aggregate and precast unit supply rates, sea conditions, environmental compliance constraints, and the financing timeline. The schedule applies to future works under the revised plan and will take effect once the adjusted operational permit terms are approved.

Regarding works already completed, the report records that as of 11 August 2026, a total of approximately 49.7 hectares of land had been reclaimed across the eastern and western peninsulas. This represents 59.1% of the total planned area of the two peninsulas (84.04 hectares), though it does not reflect the overall readiness percentage of the entire updated development.

Public Consultations: Comments Accepted Until 23 December

The application by Ambassador Batumi Island LLC for modified operational terms and its accompanying documentation package were published on the official portal of Batumi City Hall on 26 November 2026.

Interested parties may submit written reviews, comments, and proposals regarding the updated EIA report through 23 December 2026 inclusive.

Submissions are received by the National Environmental Agency of Georgia:

  • Email: eia@mepa.gov.ge

  • Mailing address: 150 David Agmashenebeli Avenue, 0112 Tbilisi, Georgia.

The email subject line should specify the recipient as the LEPL National Environmental Agency.

The submission of an updated EIA report does not in itself imply automatic approval of the proposed revisions. The review is an administrative procedure, and public input will be evaluated prior to the final environmental decision.

Overall, the updated design for the Batumi artificial island substantially broadens the spatial scope of the development and reconfigures critical engineering solutions designed to ensure water circulation, safe flood conveyance, and storm protection. Prior to final determination, the technical and environmental rationales for the project remain open for public scrutiny.